1. FOUNDATION
Reinforced Concrete Piles and/or Raft Foundation to Engineer’s Design.
2. SUPERSTRUCTURE
Reinforced concrete using Grade 35 concrete manufactured from Portland Cement complying with SS26 steel reinforcement bar complying with SS2.
3. WALLS
a) External Wall
• Clay bricks and/or concrete blocks finished with cement plaster.
b) Internal Wall
• Clay bricks and/or concrete blocks and/or dry/lightweight wall panel finished with cement plaster.
4. ROOF
Reinforced concrete flat roof and/or metal roof. Roof structure of reinforced concrete and/or timber and/or mild steel.
5. CEILING
Skim coat with emulsion paint and/or plaster board at ceiling where applicable.
6. FINISHES
a) Wall
(i) Internal
• Ceramic/Homogenous and/or mosaic tiles to ceiling height for kitchen (visible area only) and bathrooms.
• Cement plaster for living, dining, study, family and bedroom.
(ii) External/Common Area
• Cement plaster and sand plaster and/or skim coat with emulsion.
• Selected area with Ceramic/Homogenous tiles and/or stones or any other finishes as specified by the Architect.
b) Floor
(i) Internal
• Ceramic/Homogenous tiles with tiles skirting for living, dining and kitchen.
• Ceramic/Homogenous tiles and/or stones for bathroom.
• Random teak strips for bedroom, staircase (penthouse).
(ii) External (If any)
• Ceramic/Homogenous tiles and/or stones and/or any other materials for balcony, terrace (if any) and roof terrace (if any).
(iii) Common Area
• Ceramic/Homogenous tiles/stones/cement screed and /or any other materials specified by the architect for swimming pool, serenity court yard,
yoga corner, pool deck, outdoor dining / BBQ area, jacuzzi, shower area, driveway, carpark, walkway, corridor, lobby, apron and terrace.
• Cement screed with nosing tiles, and/or Ceramic/Homogenous tiles and/or stones for staircase / staircase storey shelter.
7. WINDOWS
Aluminium with glass.
8. DOORS
Aluminium with glass/acrylic and/or decorative timber and/or decorative timber with glass panel and/or glass panel.
9. SANITARY WARES/ FITTINGS
a) Internal Area
(i) Bathroom
- 1 shower with shower screen, overhead shower and shower/bath mixer
- 1 vanity top complete with basin and basin mixer
- 1 water closet
- 1 mirror
- 1 paper holder
(ii) Kitchen
- 1 sink complete with a sink mixer
10. ELECTRICAL INSTALLATION
All electrical wiring to be in concealed conduits and main in surface trunking/ pipes. Where there is a false ceiling, the electrical wiring above false ceiling is in exposed conduits. If required, mechanical ventilation provided in bathroom. Heater of “Ariston” or equivalent. Refer to Electrical Schedule for details.
11. TV/FM/TELEPHONE
The number of TV/FM/telephone points – please refer to the Electrical Schedule for details.
12. LIGHTNING PROTECTION
Lightning protection system shall be in accordance with Singapore Standard SSS555:2010.
13. PAINTING
Water-based emulsion paint for living, dining and bedroom. Oil based base-coat and water-based finishes finishing coat paint for external.
Water-based emulsion paint and/or oil based paint for common area.
14. WATERPROOFING
Waterproofing to bathroom, roof terrace, balcony, open terrace and planters.
15. PARKING
Surface Lots and/or Mechanized Car Parking.
16. RECREATION FACILITIES
a) Swimming Pool
b) Jacuzzi
c) Pool Deck
d) BBQ / Outdoor Dining
e) Serenity Court Yard
f) Yoga Corner
17. ADDITIONAL ITEMS
(A) AIR-CONDITIONERS : Split type air conditioner (”Daikin” or equivalent) provided in living, dining and bedroom.
(B) KITCHEN CABINET :
i) Built in Kitchen cabinet with solid surface counter top, electrical hob and hood.
ii) One stainless steel sink complete with sink mixer
(C) WARDROBES : Wardrobe and /or Pole-system provided in all Bedrooms.
(D) LOCKS : All locks are of “Vbh” or equivalent.
(E) RAILING : Mild steel for common stair railing. Steel and/or glass for other railings.
(F) LIFT : 1 passenger lift (”Kone” or equivalent) from 1st to 8th Storey.
(G) INTERCOM : Audio intercom to apartments.
Footnote:
1) Marble, Limestone and Granite:
Marble, limestone and granite are natural stone materials containing veins with tonality differences. There will be colour and markings caused by their complex mineral composition and incorporated impurities. While such materials can be pre-selected before installation, this non-conformity in the marble, limestone or granite as well as non-uniformity between pieces cannot be totally avoided. Granite tiles are pre-polished before laying
and care has been taken for their installation. However granite, being a much harder material than marble cannot be re-polished after installation. Hence some differences may be felt at the joints. The tonality and pattern of the marble, limestone or granite selected and installed shall be subject to availability.
2) Timber:
Timber is a natural material containing veins and tonal differences. Thus it is not possible to achieve total consistency of colour and grain in their selection and installation. Timber is also subject to thermal expansion and contraction beyond the control of builder and Vendor. Natural timber that is used outdoors will become bleached due to sunlight and rain. Thus, the cycle of maintenance on staining will need to be increased as
required. Notwithstanding this note, the Vendor shall remain fully responsible for the performance of its obligations under clause 10 and clause 17.
3) Materials, Fittings, Equipment, Finishes, Installations and Appliances:
The brand, colour and model of all materials, fittings, equipment, finishes, installations and appliances supplied shall be provided subject to Architect’s selection, market availability and the sole discretion of the Vendor.
4) Television and/or Internet Access:
The Purchaser is liable to pay annual fee, subscription fee and such other fees to the television and/or internet service providers or any other relevant party or any relevant authorities. The Vendor is not responsible to make arrangements with any of the said parties for the service connection for their respective channels and/ or internet access.
5) Air-conditioning system:
To ensure good working condition of the air-conditioning system, the system has to be maintained and cleaned on a regular basis by the Purchaser. This includes the cleaning of filters, clearing the condensate pipes and charging of gas. The Purchaser is advised to engage his/her own contractor to service the air-conditioning system regularly.
6) Wardrobes, Kitchen Cabinets, Fan Coil Units, Electrical Points, Door Swing Positions and Plaster Ceiling Boards:
Layout/Location of wardrobes, kitchen cabinets, fan coil units, electrical points, door swing positions and plaster ceiling boards are subject to Architect's sole discretion and final design.
7) Warranties :
Where warranties are given by the manufacturers and/or contractors and/or /suppliers of any of the equipment and/or appliances installed by the Vendor at the unit, the Vendor shall assign to the Purchaser such warranties at the time when possession of the Unit is delivered to the Purchaser.
8) Purpose of Building Projects and Restriction as to Use :
The building project is strictly for residential occupation only. Private car parks are provided. The open roof terrace/PES is not to be enclosed or roofed over.
9) Mechanized Car Parking Lots
The maintenance of the mechanized carpark will be managed by the Property Management Service Provider using the maintenance fund collected every month. This maintenance fund shall be used only for the maintenance of the mechanized carpark system arising out of normal usage. It does not cover any damages or defects caused by unauthorized usage and/or misuse of the mechanized carpark system.